Your product has the following tasks and predecessors.

Task Predecessor Average Time (sec)

A none 80

B A 80

C A 20

D B, C 30

E D 100

F E 20

G D, F 20



Use a takt time of 150 seconds and follow the “largest eligible task” heuristic rule to assign these tasks to the work stations. Show which tasks are assigned to each workstation